Heading | 04/16/2025 | SEWER | SPENCER SMITH | PARTIAL | | 4/16/2025 11:33:35 AM
Sewer from back of sidewalk to house clean out OK to Back fill
|
|
Heading | 04/16/2025 | U/G PLUMBING | SPENCER SMITH | PARTIAL | | 4/16/2025 11:32:31 AM
Underground plumbing below house and JDU slab Ok to back fill
|
|
Heading | 04/25/2025 | FORMS/FOOTING | JONATHAN THOMAS | (AE) APPROVED W/EXCE | | 4/25/2025 4:09:55 PM
contact to email Observation Letters to me.
|
|
Heading | 06/03/2025 | ROOF NAIL | NICK GONZALES | APPROVED | | |
|
Heading | 06/17/2025 | EXTERIOR LATH /WIRE | SPENCER SMITH | APPROVED | | |
|
Heading | 06/17/2025 | ROOF IN-PROG | SPENCER SMITH | APPROVED | | |
|
Heading | 06/24/2025 | ROUGH ELECTRIC | SPENCER SMITH | PARTIAL | | 6/24/2025 1:05:54 PM
Pending electrical receptacle within 2 feet of kitchen sink
7/2/2025 10:57:28 AM
Texted picture received showing requested plug installed.
|
|
Heading | 06/24/2025 | ROUGH FRAMING | SPENCER SMITH | PARTIAL | | 6/24/2025 1:05:17 PM
Pending fire caulk, or foam for top plate penetrations, floor to floor penetrations, and garage to living space penetrations.
|
|
Heading | 06/24/2025 | ROUGH MECH | SPENCER SMITH | APPROVED | | |
|
Heading | 06/24/2025 | ROUGH PLMG | SPENCER SMITH | APPROVED | | |
|
Heading | 06/26/2025 | ROUGH FRAMING | SPENCER SMITH | APPROVED | | |
|
Heading | 06/27/2025 | INSULATION | DAVID COOKS | APPROVED | | |
|
Heading | 06/27/2025 | WATER SERVICE | DAVID COOKS | APPROVED | | |
|
Heading | 07/02/2025 | ROUGH ELECTRIC | JONATHAN THOMAS | APPROVED - VIRTUAL | | |
|
Heading | 07/02/2025 | SHEETROCK | JONATHAN THOMAS | APPROVED - VIRTUAL | | |
|