Permit No. B25-0022 Permit Type   ALTERATIONS_COMMERCIAL Site Address   160 BIRCH ST
REDWOOD CITY, CA 94062
Applied   01/03/2025 Applicant   Barber Construction
Approved   04/25/2025 Owner   CHING ALTON TR
Issued   04/25/2025 Contractor   Barber Construction
Parent Permit No.   Description   Tenant Improvement for Dental Office
  Notes  
 
Date of Inspection Inspection Type Inspector Result Remarks Notes

Heading 04/30/2025ROUGH ELECTRICTINO PADILLAAPPROVEDArmando 650-389-38684/28/2025 10:50:07 AM AM requested

Heading 04/30/2025ROUGH FRAMINGTINO PADILLA(AE) APPROVED W/EXCEArmando 650-389-38684/28/2025 10:50:26 AM AM requested 4/30/2025 4:41:28 PM Approved with exception pending epoxy rebar and vapor barrier.

Heading 04/30/2025ROUGH MECHTINO PADILLACANCELLEDArmando 650-389-38684/28/2025 10:50:17 AM AM requested

Heading 04/30/2025ROUGH PLMGTINO PADILLAAPPROVEDArmando 650-389-38684/28/2025 10:50:37 AM AM requested

Heading 04/30/2025U/F PLUMBINGTINO PADILLAAPPROVED

Heading 04/30/2025U/G ELECTRICTINO PADILLAAPPROVED

Heading 05/05/2025SLABJONATHAN THOMASAPPROVED9:30 Armando 650-389-38684/30/2025 2:03:08 PM AM requested

Heading 05/08/2025SHEETROCKDAVID COOKSAPPROVEDDaniel 408-595-59245/7/2025 12:20:41 PM AM requested

Heading 07/02/2025**FINAL BLDGSPENCER SMITHCORRECTIONSArmando 650-389-38686/27/2025 3:16:47 PM AM requested 7/2/2025 8:16:14 AM CALLED BOTH CONTRACTORS AND OWNERS AND LEFT VOICEMAILS 8AM. NOTICED ON PLANS, GENERAL NOTES THAT A FIRE PERMIT IS REQUIRED FOR THE FIRE SPRINKLERS, KNOX BOX AND EMERGENY TELEPHONE. THOSE WILL NEED TO BE SUBMITTED, REVIEWED, APPROVED AND FIRE PERMIT FINALED BEFORE BUILDING FINAL INSPECTION CAN BE RESCHEDULED. 7/2/2025 9:52:41 AM Correction to comment above. With the proof plans for fire review, sprinkler permit not required. Contractor still needs to get title 24 and Potentially pending fire egress inspection before building final. 7/2/2025 4:29:12 PM CONFIMRED FIRE LIFE SAFETY FINAL INSPECTION NEEDED BEFORE BLDG FINAL.