Permit Details
Permit No. B24-2167 Permit Type   SFR BUILDING Site Address   158 WARWICK ST
REDWOOD CITY, CA 94062
Applied   10/11/2024 Applicant   Bahman Ghassemzadeh
Approved   01/22/2025 Owner   VOEGELE JASON & ALICE
Issued   01/23/2025 Contractor   Bahman Ghassemzadeh
Parent Permit No.   Description   Addition of Attached Garage, Bedroom, Interior Remodel
  Notes  
 
Date of Inspection Inspection Type Inspector Result Remarks Notes

Heading 02/20/2025FORMS/FOOTINGSPENCER SMITHAPPROVEDBahman 650-678-02342/18/2025 9:23:38 AM PM requested 2/20/2025 2:39:23 PM Forms and fillings approved for addition.

Heading 03/04/2025U/F FRAMINGSPENCER SMITHNOT READYeTRAKiT Inspection Request2/17/2025 2:57:46 PM 2/17/2025 2:57 PM Bahman Ghassemzadeh Contact Name: Bahman Ghassemzadeh Site Address: 158 WARWICK ST Phone: 6506780234 e-Mail: bahman@bgdesignbuild.com 3/4/2025 1:37:28 PM Not ready, ran into dry rot from the existing mud seals,

Heading 03/11/2025FORMS/FOOTINGSPENCER SMITHCANCELLEDBahman 650-678-02343/5/2025 2:58:33 PM PM requested 3/11/2025 3:45:37 PM Not ready

Heading 03/18/2025FORMS/FOOTINGSPENCER SMITHAPPROVEDBahman 650-678-02343/17/2025 8:38:26 AM PM requested 3/18/2025 2:20:05 PM Forms and footings approved for garage and front of house

Heading 04/28/2025U/F FRAMINGNICK GONZALESAPPROVED11-1 Bahman 650-678-0234

Heading 04/28/2025U/F INSULATIONNICK GONZALESPARTIALBahman 650-678-02344/28/2025 4:17:47 PM - Contractor shall provide detailed photos of wire supports under batt under floor insulation

Heading 04/28/2025U/F PLUMBINGNICK GONZALESCORRECTIONSBahman 650-678-02344/28/2025 4:20:44 PM - Provide revision to approved plans and acquire city approval for relocation of gas fueled fireplace to be installed at new addition with a 3/4" gas line supply - Gas line was not under test at the time of inspection and will be tested at sheetrock inspection (contractor proposed full test to be done at sheetrock)

Heading 06/27/2025INTERIOR SHEARDAVID COOKSPARTIALBahman 650-678-02346/27/2025 4:55:26 PM Area of inspection highlighted on the plans - inspected interior shear side only Corrections: Nailing spacing inaccurate in arears on exterior side

Heading 06/27/2025ROUGH ELECTRICDAVID COOKSPARTIAL6/27/2025 4:56:27 PM Area of inspected highlight on the plans

Heading 06/27/2025ROUGH FRAMINGDAVID COOKSPARTIAL6/27/2025 5:05:38 PM Partial rough framing inspection as highlighted on the plans, below attic Corrections: Draft Stop - Blocking around drop ceiling and sealing of penetrations

Heading 06/27/2025ROUGH PLMGDAVID COOKSPARTIAL6/27/2025 4:58:53 PM Areas of inspection highlighted on the plans

Heading 06/30/2025INSULATIONTINO PADILLAAPPROVEDBahman 650-678-02346/30/2025 2:51:46 PM Draft stopping completed, corrections completed by contractor, insulation approved.

Heading 07/02/2025SHOWER PANJONATHAN THOMASPARTIAL - VIRTUALBahman 650-678-02347/2/2025 9:18:52 AM 3 pans 7/2/2025 9:20:21 AM Master Bathroom to be done later.

HeadingSHEETROCKNICK GONZALES11:30-1:30 Bahman 650-678-0234