Permit No. ADU22-0045 Permit Type   SFR BUILDING Site Address   514 RUBY ST
REDWOOD CITY, CA 94062-2232
Applied   09/01/2022 Applicant   ADU COLLECTIVE
Approved   01/11/2023 Owner   WEST MARGARET E TR
Issued   01/23/2023 Contractor   owner builder
Parent Permit No.   Description   789sf ADU
  Notes   (5/1/2023 3:11 PM AS2) REV1 - 1 hr fire rated wall detail
 
Date of Inspection Inspection Type Inspector Result Remarks Notes

Heading 12/22/2022PRE-SITEDAVID COOKSPERFORMEDjessica 415-823-321312/22/2022 12:00:00 AM Note: Brick fireplace extends out on the right side of the main house, not shown on the drawing of the site plan. Fireplace extends out 18" at 60" long within 43" of the property line.

Heading 02/09/2023FORMS/FOOTINGRYAN FERGUSONPARTIALMike 650-921-88392/9/2023 12:00:00 AM Partial pending EOR letter for slight field changed in rebar layout at one section of interior footings. Recived a verbal ok from EOR on site Contractor provide setback letter

Heading 02/15/2023FORMS/FOOTINGRYAN FERGUSONAPPROVED2/16/2023 12:00:00 AM See attached eor letter and set back letter

Heading 02/23/2023SLABTINO PADILLANOT READYWilliam 650-670-21812/23/2023 12:00:00 AM Will call for underground plumbing under test for ADU. (2/23/2023 12:15 PM LTP) (2/9/2023 4:53 PM RWF) Partial pending EOR letter for slight field changed in rebar layout at one section of interior footings. Recived a verbal ok from EOR on site Contractor provide setback letter

Heading 02/23/2023U/G PlumbingTINO PADILLAPARTIAL 2/9/2023 4:53 PM RWF) Partial pending EOR letter for slight field changed in rebar layout at one section of interior footings. Recived a verbal ok from EOR on site Contractor provide setback letter WIll call for undergrond pluming test, all plumbing touchng concrete or stubup must be wrapped, all plumbing encased in crocrete must be wrapped

Heading 06/09/2023EXTERIOR SHEARBRIAN PEZZULICHAPPROVEDMike 650-921-8839

Heading 06/22/2023ROOF IN-PROGTOM GRAHAMPARTIALMike Harrison 650-921-88396/23/2023 1:45:25 PM Pending approved detail for skylight framing

Heading 07/12/2023SLABRYAN FERGUSONAPPROVEDMike 650-921-8839

Heading 07/13/2023FORMS/FOOTINGRYAN FERGUSONAPPROVEDMike Harrison 650-921-8839

Heading 10/19/2023OTHERBRIAN PEZZULICHAPPROVEDMike 650-921-883910/13/2023 12:49:09 PM partial 10/13/2023 2:39:44 PM soffet 10/19/2023 4:13:48 PM under eave fire rated sheathing installed

Heading 12/01/2023OTHERBRIAN PEZZULICHAPPROVEDMike 650-921-883912/1/2023 1:21:04 PM soffit / fire proof 12/1/2023 4:13:18 PM Ok to cover with soffit trim

Heading 04/05/2024ROUGH ELECTRICJONATHAN THOMASCORRECTIONS1-3 William 650-670-21814/1/2024 10:51:24 AM PM preferred :) 4/5/2024 3:41:01 PM install exterior receptacles as per print or update print install master switch at mini-splits as per prints

Heading 04/05/2024ROUGH FRAMINGJONATHAN THOMASCORRECTIONS4/5/2024 3:39:14 PM install A35's in east wall as per prints

Heading 04/05/2024ROUGH MECHJONATHAN THOMASAPPROVED4/1/2024 10:51:06 AM PM preferred :)

Heading 05/08/2024INSULATIONNICK GONZALESPARTIAL11:30 William 650-670-21815/2/2024 4:14:47 PM PM/Thomas requested 5/8/2024 3:48:19 PM - Pending installation of stairs due to sizing and spacing - A resubmittal will be done for city approval for the stairs, and removal of a pocket door - Provide a new front and rear exterior receptacle (providing a rear receptacle will also cover a service receptacle needing to be installed within 25' of the condenser) - Insulation for exterior walls was VIF only at locations that are going to have the wall mounted heat pumps (insulation needed to inspected to allow the drywall to be installed to mount the new units)

Heading 05/08/2024ROUGH ELECTRICNICK GONZALESCORRECTIONS5/8/2024 3:48:06 PM - Pending installation of stairs due to sizing and spacing - A resubmittal will be done for city approval for the stairs, and removal of a pocket door - Provide a new front and rear exterior receptacle (providing a rear receptacle will also cover a service receptacle needing to be installed within 25' of the condenser) - Insulation for exterior walls was VIF only at locations that are going to have the wall mounted heat pumps (insulation needed to inspected to allow the drywall to be installed to mount the new units)

Heading 05/08/2024ROUGH FRAMINGNICK GONZALESCORRECTIONS5/8/2024 3:47:55 PM - Pending installation of stairs due to sizing and spacing - A resubmittal will be done for city approval for the stairs, and removal of a pocket door - Provide a new front and rear exterior receptacle (providing a rear receptacle will also cover a service receptacle needing to be installed within 25' of the condenser) - Insulation for exterior walls was VIF only at locations that are going to have the wall mounted heat pumps (insulation needed to inspected to allow the drywall to be installed to mount the new units)

Heading 07/03/2024GAS TESTJONATHAN THOMASAPPROVED

Heading 07/03/2024ROUGH PLMGJONATHAN THOMASAPPROVED12 William 650-670-21817/1/2024 4:29:51 PM PM Requested

Heading 08/22/2024INSULATIONDAVID COOKS(AE) APPROVED W/EXCEWilliam 650-670-21818/20/2024 4:39:57 PM PM requested 8/22/2024 4:42:02 PM Exception: Add insulation bats between joist at the exterior wall at the end blocking behind the stairs beneath the loft floor - submit photos 9/4/2024 9:26:01 AM Corrections complete 8/28/24

Heading 09/11/2024SHEETROCKNICK GONZALESAPPROVEDWilliam 650-670-21819/9/2024 3:29:52 PM PM Requested "Sheetrock screw" 9/17/2024 7:22:17 AM wet walls in shower OK

Heading 10/23/2024INTERIOR LATH /WIREJONATHAN THOMASAPPROVED - VIRTUALWilliam 650-670-218110/21/2024 10:40:53 AM PM requested

Heading 10/23/2024SHOWER PANJONATHAN THOMASAPPROVED - VIRTUALWilliam 650-670-218110/21/2024 10:41:06 AM PM requested

Heading 10/29/2024GAS TESTNICK GONZALESAPPROVED10/29/2024 4:14:11 PM gas test for in walls lines for ADU held pressure + UG gas line that ties into existing main held 10 PSI for minutes

Heading 10/29/2024U/G GAS PIPINGNICK GONZALESPARTIAL1:30 William 650-670-218110/28/2024 8:17:20 AM PM requested 10/29/2024 4:15:17 PM - Will provide photos of water line being strapped under primary residence - UG installation was OK

Heading 10/29/2024WATER SERVICENICK GONZALESPARTIALWilliam 650-670-218110/28/2024 8:17:30 AM PM requested 10/29/2024 4:12:33 PM water service for ADU (tied into existing main) OK tie in was completed at stub up to primary residence 10/29/2024 4:14:51 PM - Will provide photos of water line being strapped under primary residence

Heading 05/22/2025**FINAL BLDGDAVID COOKSCORRECTIONSWilliam 650-670-21815/22/2025 4:08:42 PM Corrections: 1. Add address signage - one at entry frontage outside of gate visible from the streets and one at entry to the ADU - per CRC 5/22/2025 4:11:14 PM 2. Resident will need to install kitchen cabinets and stove and hood vent